beginning. house in batangas area

making a home.
30 Pins3 Followers
28. from the roof. before playwood sheets

28. from the roof. before playwood sheets

27. support for the roof (before the concrete)

27. support for the roof (before the concrete)

26. making a beam who will cover over all walls and openings in the constructions. the beam are 120cm high and 25cm thick. 16mm steel inside. multiple layers in system.

26. making a beam who will cover over all walls and openings in the constructions. the beam are 120cm high and 25cm thick. 16mm steel inside. multiple layers in system.

25. the walls is raising. double bricks are been using with steel vertical and horizontal i layers. 25cm thick. around 30cm when finished

25. the walls is raising. double bricks are been using with steel vertical and horizontal i layers. 25cm thick. around 30cm when finished

24. bringing the materials opp to the plot. preparing for the walls and beams inside/outside the house

24. bringing the materials opp to the plot. preparing for the walls and beams inside/outside the house

23. septic tank

23. septic tank

22. septic tank

22. septic tank

21. marking on the floor with color green and yellow.  for walls, doors, windows, and openings in the roof

21. marking on the floor with color green and yellow. for walls, doors, windows, and openings in the roof

20. finally finish the concrete flooring

20. finally finish the concrete flooring

19. double steel net in the ground before layer of 20 cm concrete. electrical and advance german plumbing system are in the ground under the steel net. net 20cm x 20cm and 10mm thick

19. double steel net in the ground before layer of 20 cm concrete. electrical and advance german plumbing system are in the ground under the steel net. net 20cm x 20cm and 10mm thick

18. filling the inside with stones, gravel and the some soil. the ground level are 20 meters long and 8 meters wide.

18. filling the inside with stones, gravel and the some soil. the ground level are 20 meters long and 8 meters wide.

17. ground beam, pilar and the wall, are now soon finish. we are watering the concrete. so its not drying to fast

17. ground beam, pilar and the wall, are now soon finish. we are watering the concrete. so its not drying to fast

16. second rom under the house

16. second rom under the house

15. technical rom under the bath. fitting the plumbing for water and toilets

15. technical rom under the bath. fitting the plumbing for water and toilets

14. fitting the water system to the beam and the wall.

14. fitting the water system to the beam and the wall.

13. preparing for the water waste, drain and toilets

13. preparing for the water waste, drain and toilets